Through London: the making of Thameslink

A discarded Victorian route carried passenger trains across London again in 1988. Its success set off a thirty-year struggle to make room for more trains, through a city that could not stop for the builders.

Blackfriars station stretches across the River Thames, seen from Tate Modern on the south bank.
Blackfriars station across the Thames, July 2016.1

A passage left behind

On March 19, 1986, a visitor walked south from Farringdon into a railway that had lost its rails. Debris covered the track bed. Discarded signals lay among the rubbish. In former carriage sidings, separated from the running tunnels, at least two abandoned road cars were rusting. One was recognizable as a Vauxhall Victor.2

The account appeared in the London Underground Railway Society’s journal. Its subject was Snow Hill, the short connection through which British Rail intended to send passenger trains across London. Work had begun on its return. For the moment, the route still contained the wreckage of its previous life.

Earlier generations had already excavated a passage through the center of London. Restoring it could join suburban lines on opposite sides of the capital. A passenger arriving from Bedford could continue to Blackfriars, Gatwick or Brighton. The difficulty was making those separate railways behave as one.

A railway across London

North at top · South at bottom

Thameslink in 1988: selected stations and connections The passenger route connects Bedford, Luton and St Albans with King’s Cross Thameslink, Farringdon and Blackfriars, crosses the Thames, then continues through London Bridge, East Croydon and Gatwick Airport to Brighton. The restored Snow Hill link is between Farringdon and Blackfriars. City Thameslink and the later St Pancras station are absent in this stage. Thames Bedford Luton St Albans Farringdon Blackfriars LondonBridge East Croydon Gatwick Airport Brighton King’s Cross Thameslink Snow Hill link

16 May 1988

Bedford to Brighton

Restoring the Snow Hill connection joined the northern and southern railways into a passenger route through London.

Trains called at King’s Cross Thameslink and changed power systems at Farringdon before continuing toward Blackfriars and across the river.

Snow Hill
The short link joins the two halves.
Farringdon
Overhead electricity to the north; third rail to the south.
Selected Thameslink route

Selected connections, not to scale. The inherited view shows corridors by 1986; lines do not indicate individual train schedules. 3

The London, Chatham & Dover Railway had opened its connection to Farringdon in 1866. Trains crossed the Thames, ran above Ludgate Hill and descended through Snow Hill to meet the Metropolitan Railway. The construction had cut through a crowded city. By the First World War, the cross-London passenger services had dwindled. The remaining regular service through the tunnel ended in 1916. Freight continued until 1969. The track was lifted in 1971.4

Office columns now blocked the old Snow Hill platforms. But in September 1985, British Rail passenger planner C. Austin reported that the route’s formation remained intact and its bridges structurally sound. The trains could return even though the station could not.5

An expensive 1974 proposal had languished. British Rail and the Greater London Council studied a more limited restoration in 1983–84, as electrification brought Bedford suburban trains into the northern side of central London. The two halves were closer to being joined.56

Their electricity remained incompatible. North of Farringdon, trains collected 25,000-volt alternating current from overhead wires. To the south, a conductor rail beside the track supplied 750-volt direct current. British Rail ordered trains equipped for both. The Class 319 carried a pantograph on its roof to reach the wire and collector shoes below to contact the rail. At Farringdon, the driver would change the source of power while passengers stayed aboard.7

One train, two electrical systems

The original changeover at Farringdon, 1988

25,000 volts ACOverhead wire
Pantograph on the roof
750 volts DCThird rail beside the track
Collector shoes below
Two ways to supply the same train A simplified side view shows a pantograph reaching up to an overhead wire and collector shoes beside the wheels. The Class 319 could use either electrical supply.

The driver changed power systems at Farringdon. The Class 319 could draw electricity from above or below, so passengers stayed on the same train.

Power collection shown schematically; equipment spacing and vehicle proportions are simplified. 7

On July 1, 1985, transport minister David Mitchell announced approval for the Snow Hill link and its new trains. He gave the cost of the whole scheme as £54 million. New rolling stock on Thameslink would release other trains for routes out of Euston and Liverpool Street. The government was approving a fleet replacement and a cross-city connection together.8

That combination helped make the financial case for the link. In a terminus, a train must stop, unload, change direction and occupy a platform before setting off again. A train running through London could spend more of its working day carrying passengers. When Network SouthEast director Chris Green explained the project to transport economists in February 1987, he emphasized the vehicles saved by linking services. The tunnel work, he said, cost under £2 million. That figure described the restoration work, a small component of a scheme whose trains cost far more.9

In 1986, British Rail renamed its London and South East sector Network SouthEast. Under Green, the undertaking gained a recognizable public identity across the commuter network. Its commercial responsibilities included investment and costs, while British Rail’s regional organizations continued operating the railway. Success required the planners, fleet builders and regional operating staff to deliver their parts together. Green inherited an approved project. The council, railway planners and ministers had already helped bring it to that point.910

The restored connection opened for testing and training on August 12, 1987. The trains were late. Delayed deliveries of the Class 319s pushed the intended October introduction into the following spring. A usable passage under London could not carry a public service until the fleet was ready.11

On April 25, 1988, Princess Anne visited Blackfriars for the ceremonial opening. The Evening Standard reported that five hundred schoolchildren cheered her arrival. British Rail chairman Sir Robert Reid accompanied her. The occasion also marked Save the Children Week. The newspaper presented the coming service as a way to travel straight through the capital.12

The public timetable began on May 16. The Guardian’s Matthew Engel tried it. At King’s Cross Thameslink, he found platforms still missing many of their station-name signs. His train arrived fifteen minutes late. At Blackfriars, trouble with the pantograph forced passengers off, then back on. A further delay followed at Croydon. At Gatwick, the train was taken out of service. The next one was late too. Engel finally reached Brighton at 11:37 a.m., eighty-two minutes behind schedule.13

The reported journey exposed how much more a through-service required than reopened track. Every disruption along the way became part of the same trip. Even the promised refreshment trolleys had yet to be built.

South London passengers could now reach Farringdon and King’s Cross directly. Passengers from the north could continue to Blackfriars. Many useful journeys crossed only part of the newly connected railway.5

Within its first year, travel between the northern and southern parts of the newly connected network increased by 300 percent. That was a measure of journeys across the former divide, rather than growth across the entire railway. The opening had revealed demand for connections that the old pattern of separate terminals had made awkward.14

A yellow-fronted Class 319 approaches the old Blackfriars platforms beside an older train at a terminal platform.
A northbound Class 319 approaches Blackfriars on May 22, 1989. An older electric train stands at a terminal platform on the left.15 Select photograph to enlarge.

The route itself continued changing. In 1990, the viaduct over Ludgate Hill came down and the railway descended below street level. Holborn Viaduct terminus closed, replaced by the station eventually named City Thameslink. The restored cross-London service had already begun reshaping the infrastructure that made it possible.4

The railway through the market

At St Albans, Lee-Anne Stubbings could not get onto the 8:21. The Evening Standard’s reporters could not board either. The train was full. Their account, published in May 2000, promised twelve-car trains and twenty-four trains an hour by 2006. 16

Plans for more capacity had begun in 1989, a year after the cross-London service opened. Its success confronted the limits of the railway it had inherited. By 1996, the government identified bottlenecks around London Bridge as the principal restriction on a route that could accommodate no more than six trains an hour in each direction through central London. The proposed expansion would quadruple that frequency. It required additional tracks through Borough Market, rebuilt stations and a connection bringing Great Northern trains into the network. Transport Secretary Sir George Young expected services within six years, subject to planning permission and the progress of another enormous railway project.1718

British Rail itself had been divided. In 1994, Railtrack took over the infrastructure, while passenger services were separated for franchising to private operators. The expanded railway would have to be assembled across those separate responsibilities.19

The new Thameslink station beneath St Pancras depended on the Channel Tunnel Rail Link. That project’s promoter would build the station structure. Railtrack would fit it out and undertake other Thameslink infrastructure. A delay in one railway could therefore hold up the other. By 1999, a parliamentary committee recorded that slippage on the Channel Tunnel Rail Link had moved Thameslink’s projected opening from 2004 to 2006.1820

South of the river, the extra tracks required land where people already lived and worked.

In the summer of 2000, opponents gathered for a press conference inside the threatened Wheatsheaf pub. Solicitor Benedict Birnberg represented residents around Southwark Cathedral. He advocated expanding the route through Herne Hill. The alternative offered a way to argue for better transport while resisting the destruction anticipated around Borough Market. Globe artistic director Mark Rylance expressed what the neighborhood stood to lose: “We have a right to a little town centre.” Residents’ representatives feared years of construction disruption. The inquiry was sitting nearby at Bankside House.21

The dispute reached beyond whether a viaduct could carry more trains. It concerned the buildings removed to make room, the streets left afterward and the ability of a working neighborhood to survive the transition. Inspector David Ward accepted the scheme’s substantial transport, economic and regeneration benefits. His report nevertheless found the design of London Bridge station inadequate. Proposals were missing for replacing demolished buildings in the Borough High Street Conservation Area. The development above the Blackfriars concourse also left an unacceptable gap. 2223

By the time ministers considered the report, Network Rail had taken over Railtrack’s infrastructure business.19

The Strategic Rail Authority sought approval for a scheme divided into two phases, with conditions attached to settle the outstanding issues. In January 2003, the government deferred its decision. Fresh applications and an updated environmental statement were required. The inquiry would have to reopen.22

Development funding itself was unreliable. In later parliamentary evidence, the Department for Transport’s rail projects director explained that intermittent development funding had impeded progress through the inquiries. The money needed to complete the planning work had arrived unevenly.24

By November 2005, the reopened inquiry was considering revised proposals, and the project’s name had become an embarrassment. In the Commons, Alistair Darling acknowledged that Thameslink 2000 was five years past its intended completion: “the name is a bit of a joke.” Simon Hughes, the local MP, had given evidence against the scheme and pressed him on alternative routes. Darling insisted on the need for the railway while awaiting the inquiry’s decision.25

In October 2006, ministers accepted that the earlier deficiencies had been addressed. They granted planning permission and the necessary powers. Funding still required a separate decision. At Borough Market, campaigners continued collecting signatures from Saturday shoppers. They believed that remaining decision left an opening to change the route. Jackie Power, of the local campaign, said: “While the buildings are still standing there’s still hope, isn’t there?”2627

On July 24, 2007, Transport Secretary Ruth Kelly announced the funding commitment: £5.5 billion for Thameslink. Eighteen years after the first capacity proposals, the project had both permission and government backing. Delivering the promised space on St Albans trains would mean building through the neighborhood that campaigners had been fighting to preserve.28

From proposal to funding

  1. Expansion proposedPlans begin for more capacity.
  2. Decision deferredRevised designs and a reopened inquiry are required.
  3. Planning powers grantedPermission is secured. Funding remains undecided.
  4. Funding committedThe government announces £5.5 billion.
Eighteen years separate the first expansion proposals and the funding commitment. 17222628

Building around the trains

The funded Programme promised completion in 2015. Longer trains would arrive first, followed by the more difficult reconstruction around London Bridge.29

In December 2007, services moved from the cramped King’s Cross Thameslink station into new platforms beneath St Pancras International. Lifts and escalators reached the longer, wider platforms. Passengers arriving from Brighton or St Albans could connect there with Eurostar. The station structure built with the Channel Tunnel Rail Link had become a working interchange.30

The sequence soon began to slip. By December 2009, Network Rail estimated that the second phase could exceed its initial infrastructure budget by 31 percent. Completion might take until 2020. The Department for Transport reconsidered how much railway it could afford to build. Stopping after the first phase would leave expensive work delivering too little benefit. London Bridge would still need renewal. In 2010, the government moved completion to 2018. The compromise gave engineers more time and spread expenditure beyond the immediate spending period.31

Green steel viaduct beams and concrete columns rise between existing buildings beside a narrow London street.
The first section of the new Borough Market viaduct takes shape among existing buildings, looking toward Stoney Street, January 13, 2011.32 Select photograph to enlarge.

On the first Saturday of the May bank-holiday weekend in 2011, work began at two in the morning to move a new railway bridge across Borough High Street. It was approximately 236 feet long. Specialist machinery advanced it little more than a foot a minute before it was lowered into position. The road reopened at five on Tuesday morning.33

The bridge addressed a restriction that had survived the 1988 reopening. West of London Bridge, trains toward Charing Cross and Blackfriars shared a narrow approach. The additional viaduct would give them separate tracks. Network Rail had created replacement trading space for Borough Market vendors before construction began.33

At Blackfriars, engineers extended the platforms across the Thames to accommodate twelve-car trains. A new entrance on the south bank opened in December 2011. Within months, Network Rail reported that it accounted for 40 percent of people entering or leaving the station. Passengers could choose the bank nearest their destination. The bridge itself had become the station.34

The new bridge at Borough had to wait. Four years later, in September 2015, the first rails and ballast arrived. Charing Cross trains moved onto the new viaduct in January 2016. The older tracks could then be rebuilt for Thameslink. Each improvement created the space for the next. A completed bridge could stand unused until the surrounding railway was ready to release it.35

At London Bridge, that surrounding railway concealed its own history. The station had grown through generations of alterations. Wartime bomb damage had been repaired quickly to restore services, and the drawings did not fully record what lay beneath the operating tracks. Investigating the structure thoroughly meant interrupting the trains that still used it.36

Simon Blanchflower, Network Rail’s senior officer responsible for Thameslink, later described the method to Parliament: “six sequential slices across the station.” His teams rebuilt one section after another while maintaining a working station alongside them. Station construction had to meet the dates when tracks could be rearranged and signals commissioned during holiday closures. Unexpected conditions made the work more complicated. Accelerating construction to preserve the sequence increased the cost.36

MPs challenged that explanation. Nigel Mills wanted to know why the difficulty had not been understood earlier. Blanchflower said the risks had been recognized, but the conditions uncovered were worse than anticipated. The National Audit Office accepted the difficulties of investigating a live station while also finding that Network Rail had controlled changes poorly. By 2017 the infrastructure budget stood £474 million above its 2012 level, predominantly because of London Bridge.3637

Passengers paid in time as well. Platforms and tracks taken out of service left less room to recover when trains ran late. In January 2015, failures in new track equipment combined with faulty assumptions underlying the timetable to produce delays and crowding. 37

East of the station, engineers were changing how the lines crossed. At Bermondsey, trains arriving from Kent and Sussex had intersected at junctions. One movement had to wait for another. The new dive-under separated their paths vertically. Charing Cross trains could pass beneath the routes used by Southern and Thameslink. After the August 2017 closure, the Charing Cross lines reached their final alignment. This freed the way for Thameslink’s dedicated tracks.38

London Bridge, rebuilt

Before the Thameslink Programme

Borough MarketWest of the station

ThameslinkCharing Cross

One shared approach

Thameslink and Charing Cross trains competed for space on the existing viaduct.

London BridgePlatforms

Through platforms
6
Terminal platforms
9

15 platforms in all

Six platforms carried trains onward across London. Nine served trains ending their journey here.

BermondseyEast of the station

ThameslinkSouthernCharing Cross

Crossings at track level

Intersecting routes meant one train could have to wait while another crossed its path.

After the rebuilding

Borough MarketWest of the station

ThameslinkCharing Cross

Old viaduct: Thameslink · New viaduct: Charing Cross

Moving Charing Cross trains onto the new viaduct released the old approach for Thameslink.

London BridgePlatforms

Through platforms
9
Terminal platforms
6

15 platforms in all

Three more platforms served through trains. A common concourse connected all fifteen.

BermondseyEast of the station

ThameslinkSouthernCharing Cross

Charing Cross passes underneath

The dive-under separated Charing Cross trains from the routes used by Thameslink and Southern.

Selected routes only. Schematic, not a track plan; line positions do not show geographic alignment or platform order. Platform counts cover the whole station. 39

On January 2, 2018, the final section of London Bridge’s new concourse opened to the public. For the first time, a common concourse connected all fifteen platforms. New entrances joined the north and south sides of the station. Five years of construction had produced a common concourse beneath the tracks, with easier movement through the station and fewer conflicts between the trains above.40

Passengers cross London Bridge’s spacious new concourse beneath a wood-lined ceiling, with stairs and escalators rising to the platforms.
Passengers use London Bridge’s rebuilt concourse on January 5, 2018, three days after its final section opened.41 Select photograph to enlarge.

North of St Pancras, the Canal Tunnels connected the East Coast Main Line to the cross-London route. By March 2018, preview passenger services had brought Cambridge and Peterborough into the through-service. The northern side of the network now reached beyond the Bedford line that had supplied the original trains.42

The train and the timetable

The next constraint was time between trains. Siemens built a fleet of 115 Class 700s, with eight or twelve cars apiece. New cab signaling and automatic operation would control their acceleration and braking through central London. Consistent movements would allow more trains to fit into the same passage. The first entered passenger service in June 2016. The last rolled off the production line in Germany by March 2018.43

On March 17, 2018, at 1:53 p.m., train 700019 brought itself to a stop at St Pancras. The eight-car train was heading south to Three Bridges. It had changed into the new signaling system and automatic operation on its approach from Kentish Town. Its driver checked the platform and closed the doors, then selected automatic operation again.44

The train continued through Farringdon and City Thameslink to Blackfriars before leaving the automatic system toward Elephant & Castle. Almost two hundred testing shifts had preceded the achievement. Jim Doughty, systems integration manager at operator Govia Thameslink Railway (GTR), had worked with teams from Network Rail and Siemens. Together they had made automatic operation work on a passenger train through London.44

On May 20, the new timetable began. Cancellations and delays followed.

An effort to reduce the risk had helped create another. GTR had proposed introducing the expanded service more gradually in April 2017. Formal ministerial approval came at the end of October. Reducing the initial service from twenty to eighteen trains an hour required complex changes because Thameslink’s trains fitted among other services on several main lines. The work involved far more than deleting two departures.45

GTR received its revised timetable on April 9, 2018. Driver rosters were posted on May 18, two days before the new service began. The company had already known it would struggle to supply enough fully trained drivers. Its proposed remedies included borrowing drivers and relying on rest-day working. The regulator found that preparations had not been adequately tested against the risks. The parliamentary inquiry endorsed its conclusion: “no one took charge.”45

Network Rail’s timetable planners had failed to manage the combined risks. The Department for Transport and the Office of Rail and Road had accepted assurances without sufficient challenge. The regulator’s own inquiry identified failures throughout the system.46

Before Parliament, GTR chief executive Charles Horton described the resulting mismatch between drivers’ skills and the work assigned to them. A train could possess the necessary equipment while its operator lacked a workable arrangement for getting the right driver to it.47

More trains in the same hour

Through central London, in one direction. Each mark represents one train or one available path through the railway.

10 minaverage interval

3 minaverage interval

2½ minaverage interval

Intervals are calculated as 60 minutes divided by frequency. Marks are evenly spaced for comparison; they do not reproduce a timetable. The 24-path figure describes infrastructure capacity in December 2019. The service introduced that year was 20 trains an hour. 48

Service expanded more cautiously afterward. In May 2019, the central section reached twenty trains an hour. The regulator recorded infrastructure capable of twenty-four paths by December, while calling for further improvement in reliability. Weekday trains between Cambridge and Brighton doubled from one an hour to two. The route carried them through Snow Hill, where a visitor in 1986 had found discarded signals and rusting cars. A passenger from Cambridge could now stay in the same seat through that tunnel, across the Thames and all the way to Brighton.49

Endnotes
  1. Alison M Wheeler, Blackfriars station from Tate Modern, July 5, 2016. Photograph licensed CC BY-SA 4.0; resized, otherwise unchanged. ↩
  2. “Snow Hill Revisited,” Underground News 293, May 1986, pp. 59–60, in the London Underground Railway Society’s 1986 archive. The report describes conditions on March 19, 1986. ↩
  3. London Transport Museum, “Thameslink: a history through the city”, July 24, 2019; Network Rail, St Pancras Thameslink station opening, December 10, 2007, and Canal Tunnels connection, 2013; Govia Thameslink Railway, preview passenger services, March 8, 2018. Route diagrams show selected connections, not the complete network or a geographic map. ↩
  4. Laura Sleath, London Transport Museum, “Thameslink: a history through the city”, July 24, 2019; C. Austin’s September 1985 address, Underground News 287, November 1985, pp. 137–38, 1985 archive. ↩1 ↩2
  5. C. Austin, British Rail passenger planning officer, September 1985 address, Underground News 287, pp. 137–38, 1985 archive. This contemporary account distinguishes the limited restoration from the more extensive 1974 proposal. ↩1 ↩2 ↩3
  6. House of Commons, Bedford–St Pancras railway line, February 21, 1983; Austin’s address records electric services reaching Moorgate in 1983. ↩
  7. GEC Traction, Class 319 dual-voltage train brochure; Austin’s address, pp. 137–38. ↩1 ↩2
  8. David Mitchell, Snow Hill Tunnel, written answer, July 1, 1985. The £54 million is the contemporary approved scheme estimate, including trains. ↩
  9. Graham Scholefield’s report of Chris Green’s February 1987 address, The Transport Economist 14(4), pp. 33–45. ↩1 ↩2
  10. Science Museum Group, Network SouthEast, institutional history. ↩
  11. John McCrickard, Railway Chronology Newsletter 70, April 2012, entries for August 12 and September 2, 1987, and May 1988. Testing, ceremonial opening and the public timetable had separate dates. ↩
  12. Emma Lee-Potter, “Thameslink takes BR straight through,” Evening Standard, April 25, 1988, p. 3, newspaper scan. ↩
  13. Matthew Engel, “Just like old times on today’s railways,” The Guardian, May 17, 1988, p. 24, newspaper scan. This is the reporter’s first-day journey, not a system-wide punctuality measure. ↩
  14. Network Rail, Thameslink 2000: Statement of Reasons, October 2005, p. 28. ↩
  15. Ben Brooksbank, A northbound Class 319 approaches Blackfriars on May 22, 1989. An older electric train stands at a terminal platform on the left., licensed CC BY-SA 2.0. Resized and compressed for display; no crop or retouching. ↩
  16. “Commuter Watch,” May 9, 2000, p. 18, contemporary newspaper report. ↩
  17. National Audit Office, Progress in the Thameslink programme (2013), paras. 1.2–1.4, report. ↩1 ↩2
  18. Sir George Young, Commons statement, February 27, 1996, Thameslink 2000. ↩1 ↩2
  19. Network Rail, Working with railway heritage, chronology entries for April 1, 1994, and October 3, 2002. ↩1 ↩2
  20. Commons Environment, Transport and Regional Affairs Committee, Fifteenth Report (1999), paras. 45–46, Channel Tunnel Rail Link. ↩
  21. “Borough Market Thameslink threat,” in SE1, July 2000, p. 1, issue 25. ↩
  22. Christopher Leslie, written answer, January 29, 2003, Thameslink 2000; Mira Bar-Hillel, “Planners deal huge blow to £1bn Thameslink scheme,” Evening Standard, July 31, 2002, p. 4, contemporary report. ↩1 ↩2 ↩3
  23. Southwark Planning Committee, February 8, 2005, paras. 3.1–3.6, Blackfriars planning report. ↩
  24. Michael Hurn, evidence to the Public Accounts Committee, June 19, 2013, Q2, HC 296, Ev 1–2. ↩
  25. Commons exchange, November 8, 2005, Cross-London Rail Route. ↩
  26. Stephen Ladyman, written statement, October 18, 2006, col. 56WS, Thameslink 2000. ↩1 ↩2
  27. London SE1, October 28, 2006, Borough Market campaign report. ↩
  28. Ruth Kelly, Commons statement, July 24, 2007, rail strategy debate; Commons Library, Railways White Paper 2007. ↩1 ↩2
  29. House of Commons Library, Railways: Thameslink infrastructure project, January 26, 2012, pp. 2–3. ↩
  30. Network Rail, “New station within St Pancras International brings better journeys and European connections”, December 10, 2007. ↩
  31. National Audit Office, Progress in the Thameslink programme, June 5, 2013, §§1.10, 2.9–2.12. ↩
  32. Ivor the driver, The first section of the new Borough Market viaduct takes shape among existing buildings, looking toward Stoney Street, January 13, 2011., licensed CC BY-SA 3.0. Resized and compressed for display; no crop or retouching. ↩
  33. Network Rail, “New landmark bridge launched into place”, May 3, 2011. Dimensions and movement speed converted to imperial units. ↩1 ↩2
  34. Network Rail, “Countdown to completion at Blackfriars”, December 5, 2011; “Historic cartouches return to London’s South Bank”, March 2012. The latter reports the new entrance’s actual use. ↩
  35. Network Rail, “Night vision: First rails for Borough Viaduct arrive at London Bridge”, September 14, 2015. See also Network Rail, “New viaduct comes into use”, January 4, 2016. ↩
  36. Public Accounts Committee, oral evidence on the Thameslink Programme, December 6, 2017, questions 51–60. ↩1 ↩2 ↩3
  37. National Audit Office, Update on the Thameslink programme, November 23, 2017, §§2.5–2.11. Cost comparison is in 2017 prices. ↩1 ↩2
  38. Network Rail, “New junction to unlock London Bridge railway bottleneck moves closer to completion as first tracks are laid”, October 18, 2016; “New platform and tracks at London Bridge station”, September 2017. ↩
  39. Department for Transport, Thameslink Programme: baseline evaluation, March 2018, §§2.6.1–2.6.3; Network Rail, Bermondsey Dive Under, July 3, 2017, and Borough viaduct brought into use, January 4, 2016. Diagram by Liam Blank. ↩
  40. Network Rail, Annual Return 2018, p. 8. ↩
  41. DAVID HOLT, Passengers use London Bridge’s rebuilt concourse on January 5, 2018, three days after its final section opened., licensed CC BY 2.0. Resized and compressed for display; no crop or retouching. ↩
  42. Network Rail, “Thameslink tunnels to transform the railway in London and the south east”, 2013; Govia Thameslink Railway, “GTR gives passengers taste of vastly expanded services”, March 8, 2018. ↩
  43. Siemens, “Thameslink Rolling Stock Programme ahead of schedule”, March 2018; Network Rail, “Test train runs under cab signalling on Thameslink route through central London”, December 15, 2015; GTR source in note P10 explains automatic operation. ↩
  44. Govia Thameslink Railway, “World-first for ATO on mainline railway”, March 20, 2018. ↩1 ↩2
  45. House of Commons Transport Committee, Rail timetable changes: May 2018, chapter 2, December 2018, §§35–43, 51–55, 64. ↩1 ↩2
  46. Office of Rail and Road, “ORR Inquiry concludes passengers let down by rail industry failures”, September 20, 2018. ↩
  47. Transport Committee, oral evidence on rail timetable changes, June 18, 2018, Charles Horton's evidence. ↩
  48. Sir George Young, Thameslink 2000, February 27, 1996, describes a limit of six trains per hour in each direction. Office of Rail and Road, Annual assessment of Network Rail, April 2019–March 2020, §§6.27–6.28, records the twenty-train service introduced in May 2019 and infrastructure providing twenty-four paths per hour in December. Average intervals are calculations, not observed departures. ↩
  49. Office of Rail and Road, Annual assessment of Network Rail, April 2019–March 2020, July 2, 2020, §§6.27–6.28; GTR twenty-eighth supplemental access agreement decision, August 12, 2019, recording approval on April 24. ↩