Four fixes inside Penn Station make room for a third more trains

The federal government spent a year testing how many more trains New York Penn Station can move without growing an inch. Its first phase found room for a third more and found that going higher depends on trains arriving on time from across the region. This 3D model puts the station at true scale inside Midtown’s own buildings and shows, scene by scene, the four fixes that make the room and what Phase II has yet to test.

Loading the station and the city around it…
Today Model clock 7:30 AM
Trains in from the Hudson, last hour 0
Scene 1 / 13
Trains
NJ TransitALP-45DP engine, MultiLevel coaches
Long Island Rail RoadM7 electric cars
AmtrakACS-64 engine, Amfleet coaches
Commuter through trainFRA names no operator
Dark windowsempty train

The station sits under four blocks of Midtown

Penn Station’s 21 tracks and 11 platforms lie below the street between 31st and 33rd Streets, from Seventh Avenue to west of Ninth. Madison Square Garden, PENN 2, Moynihan Train Hall, and the Manhattan West towers stand on top of them.

More than 350,000 people pass through on a weekday, aboard more than 1,000 train movements. NJ Transit, the Long Island Rail Road, and Amtrak share a layout drawn in 1910, and Metro-North is on its way as a fourth tenant.

24trains per hour per direction cross the Hudson into Penn at the peak today

Six tubes feed 21 tracks

With the buildings lifted off, the track level shows. Two single-track North River tubes carry every train from New Jersey and top out near 24 an hour in the peak direction. Four East River tubes feed the east end. One Empire Connection track brings trains down the West Side from Albany.

Tracks 1 through 4 dead-end under Seventh Avenue, so every train on them has to reverse. Only Tracks 5 to 21 carry the third rail LIRR trains run on, so LIRR cannot use Tracks 1 to 4. Tracks 20 and 21 reach west only to West Side Yard.

1,000+columns hold up the buildings above and fix the track layout in place, the report finds, which is why Phase I works inside it

A train that ends here holds its platform for 22 minutes

Most NJ Transit trains terminate at Penn. Each one unloads, swaps its crew, boards a new load, runs a brake test, and heads back west. NJ Transit schedules 22 minutes for the shortest turn. The timers show each parked train counting down.

Boarding cannot start until the arriving crowd has cleared the platform and the new crew is aboard. Commuter and Amtrak dwells at Penn run more than three times longer than at its closest international peer.

Off 5:00Crew 3:00Board 9:45Pad 3:50Sweep 6:00Brake test 5:0005101522 min
FRA Phase I Report, Figure 4. Top row: riders get off, the new crew sets up, riders board, then a recovery pad. Bottom row: the crew’s sweep and brake test run alongside. Gold ticks: doors open and close.

Every turning train crosses the ones behind it

West of the platforms, trains from New Jersey pass through A Interlocking, a web of switches. A train arriving to turn and a train leaving after its turn often need the same piece of track, so one waits. Empire trains and empty trains bound for the yards cut across the same web. Red marks show where routes cross in this model.

The switches are short, so trains move at 15 mph at most. After each move, A Interlocking’s compressed-air switch machines take about 24 seconds to reset.

113conflicting moves at A Interlocking between 8 and 9 in the morning, by FRA’s count

The new tunnel doubles the pipe. The station does not grow.

The Hudson Tunnel Project, due around 2035, and rehabilitation of the 1910 tubes, due in 2038, could double trans-Hudson capacity from 24 to as many as 48 trains per hour per direction. The new tubes’ leads are lit in gold.

The report’s finding: once those investments are done, Penn Station itself, its tracks, platforms, stairs, and operating habits, becomes the binding constraint. Without changes inside, the new tunnel’s capacity goes underused.

24 → 48theoretical trans-Hudson capacity once both tunnel pairs run

First fix: give each tunnel its own tracks

FRA calls this interlocking deconfliction. The new Hudson tubes feed Tracks 1 to 4, a dead-end station just for NJ Transit trains that turn back; Empire trains keep Tracks 5 and 6. The old North River tubes line up with the middle tracks and run straight through to East River Lines 1 and 2. East River Lines 3 and 4 serve the north tracks, which run through to West Side Yard.

A delay now tends to stay inside one zone instead of rippling across the station. The model is running the Phase I morning plan, with the new tubes open.

113 → 51conflicting moves at A Interlocking, a 55 percent drop

Second fix: more ways off the platform

A train cannot leave until its riders clear the platform, and the stairs and escalators meter how fast that happens. Phase I adds up to 23 of them, 19 stairs and 4 escalators, at least one per platform, marked in blue where FRA’s Figure 11 places them. It extends Platforms 1, 2, and 3 west by 200 to 350 feet, shown in gold.

Penn’s platforms run 17 to 23 feet wide, except LIRR’s 44-foot Platform 10; FRA’s peer stations give riders about 39 feet at Utrecht Centraal and 33 at London Waterloo. FRA’s crowd model needed 11.4 minutes for the passenger exchange with today’s stairs and 9 with the added ones, which lets Phase I schedule the turn in 18.

−2.4 minaverage platform clearing and boarding time, a 28 percent cut

Third fix: let some trains keep going

A through train unloads and loads at the same time and leaves in the direction it was already heading. There is no crew walk to the other cab and no reversing move back across the interlocking. Penn already runs this way for Amtrak.

Phase I adds four regional commuter trains per hour through the station in each direction, on top of four Amtrak through trains. Their paths are drawn in gold, tunnel to tunnel, with arrows moving the way the trains do. The red paths belong to trains that end here: in from the new Hudson tubes to Tracks 1 to 4, and back out the same way.

4 + 4commuter and Amtrak through trains per hour, each direction, in Phase I

Fourth fix: one plan for the whole station

LIRR is the only Penn operator that plans every train’s track, length, and next departure in a Terminal Operating Plan. It posts 97 percent on-time performance. Amtrak ran 76 percent on time on the Northeast Corridor in 2025; NJ Transit’s Northeast Corridor Line ran 81 percent in January 2026.

The study calls for one plan covering the whole station and a standard train-start routine so trains move within seconds of getting the signal.

97%LIRR on-time performance with a Terminal Operating Plan, February 2026

The model’s last hour. Each row is a platform track, 1 at the top to 21 at the bottom; each bar is one train holding that track.

The four fixes carry a third more trains. Going higher depends on the trains arriving on time.

Together they lift the peak from 24 trains per hour per direction to 32 in the morning and 30 in the evening, inside the existing station. That is up to a third of the added capacity the earlier $16.7 billion expansion project promised, at a fraction of its cost.

Phase I tested only what fits inside the station walls. In FRA’s delay simulation, 32 trains an hour ran slightly worse than today and 30 slightly better. A plan with six Amtrak trains an hour fit the timetable but failed once late arrivals entered, so the final plans hold Amtrak to four. The report says going above 32 depends on how punctually trains arrive from across the region.

+33%peak trains through the same station in the morning, before Phase II tests what lies outside it

A second package failed its stress test

Penn Station Future merges Platforms 5 and 6 into one super-wide platform, gives up Tracks 10 and 11, and doubles commuter through-running to eight trains per hour each way at the same 32-train total. The timetable fit on paper. FRA’s dynamic simulation failed once late arrivals and congestion at LIRR’s West Side Yard entered, and FRA sent the package to Phase II.

In this model the package carries 26 or 27 of its 32 trains an hour from New Jersey even with every train on time. Here each train also arrives up to 2.5 minutes late at random, and trains held outside the station are flagged at the tunnel mouths.

8commuter through trains per hour each way, deferred to Phase II

Trains held at a tunnel mouth, last hour0Minutes lost waiting, last hour0Trains that found no slot, last hour0

The developer wants to extend east, not west

Amtrak picked Penn Transformation Partners as master developer after Phase I closed. FRA’s July Addendum records the team’s alternative to the westward extensions: push Platforms 1 and 2 up to 450 feet east beneath Seventh Avenue and the 1, 2, and 3 subway, ending in the sub-basement of the PENN 11 building. The extension is drawn in teal, through the street and the building above it.

FRA writes that going east may disrupt the station less during construction and match or beat the westward plan’s benefits. A 2021 master plan white paper places a Con Edison substation in PENN 11’s basement, where the extension would end.

450 ftthe longest eastward stretch for Platforms 1 and 2 in the developer’s concept

Phase I stopped at the station walls. Phase II goes past them.

Phase II, due in 2028, leaves the station walls and studies the Metro-North, LIRR, and NJ Transit service areas: arrival reliability, junctions, yards, train fleets, labor, and who runs the station.

The model keeps running. Switch the service plan, change its speed, put the buildings back, or select a train to read what it is doing.

Service plan
Speed
View

A third more trains, same walls

Phase I tested 86 scenarios in three kinds of models: a timetable builder, a dynamic rail simulator that adds real-world delays, and a crowd model that walks every rider to the stairs. Two packages came out the other end.

Minutes a train holds its platform: today, Phase I, Penn Station Future

Two packages

Penn Transformation Improvements Built with the station overhaul. Up to 32 trains an hour in the morning, 30 in the evening, with 4 Amtrak and 4 commuter trains running through each way. Extends Platforms 1–3 west, adds up to 23 stairs and escalators, rebuilds the Hudson Tunnel ladder, and replaces about 115 columns. Passed the dynamic simulation.

Penn Station Future Merges Platforms 5 and 6 into one wide platform and runs 8 commuter trains through each way, at the same 32-train total. Sent to Phase II after late arrivals and West Side Yard congestion broke it in simulation. No owner and no date yet.

The eleven platforms today

Eight of the eleven platforms are 17 to 20 feet wide, and a stair or escalator in the middle can take half of that. Platform 9 has no escalator at all. The last two columns show what Phase I adds: new stairs and escalators from FRA’s Figure 11, and floor space won back by clearing equipment off the platform.

PlatformTracksWidth (ft)StairsEscalatorsElevatorsPhase I stairs and escalatorsCirculation area (sq ft)Decluttering gain (sq ft)
11, 222622+213,700+880
23, 420532+213,100+660
35, 620424+312,900+360
47, 820355+217,900+580
59, 1019365+320,700+870
611, 1217464+220,900+650
713, 1420464+222,500+950
815, 1620554+219,000+830
917, 1820702+216,500+290
1018, 1944721+127,500+3,980
1120, 2120711+217,600+350

Widths and existing stairs, escalators, and elevators: April 2021 Penn Station master plan white paper, except Platform 10’s width, which follows FRA. Phase I additions: FRA Figure 11, read from its map. Circulation area and decluttering gain: FRA Phase I Report, Table 1.

You do not have to ride NJ Transit to feel this

Penn Station sets the ceiling for the busiest rail corridor in the country. What happens on its platforms reaches people who never connect it back to a staircase in Midtown.

NJ Transit riders
NJ Transit posts a departure track only once the train sits at the platform, so riders wait on the concourse until it arrives. The shorter Phase I boarding times assume the track goes up two to three minutes before arrival. Longer platforms let 10-car trains open every door on Platforms 1 to 3, where only the eight eastern cars can today; without them, those platforms would cap train length across whole NJ Transit lines.
Boston-to-Washington travelers
Every Amtrak train between Boston and Washington crosses the same switches New Jersey commuters use. Amtrak ran 76 percent on time on the Northeast Corridor in 2025. FRA’s simulation found each Amtrak train costs the station more capacity than a commuter train because intercity trains arrive less predictably, so the final plans hold Amtrak to four an hour each way. Boarding from both Moynihan and Penn cuts Amtrak’s longest platform service time from 19.3 to 10.2 minutes.
The Bronx and Westchester
Metro-North’s Penn Station Access project adds Bronx stations at Co-op City, Morris Park, Parkchester–Van Nest, and Hunts Point and brings New Haven Line trains into Penn through the East River Tunnels. Those trains need platform time too. Every minute a turning train wastes is time the Bronx competes for.
People whose jobs are not in Midtown
Office attendance fell from 78 percent in 2019 to 56 percent in 2024, the report notes. A train that continues past Penn gives a Newark rider a one-seat ride to Queens or Long Island, and a Long Islander one to Secaucus or Newark. Phase II is where FRA forecasts that market.
Anyone who cannot take stairs two at a time
Penn’s platforms average under 20 feet wide, and many of its escalators carry one person per step. Up to 23 new stairs and escalators, at least one per platform, help parents with strollers, travelers with luggage, and riders with disabilities as much as they help the timetable.
Everyone on a crowded platform
The stairs that empty a platform after each train are the same routes out in an emergency. NFPA 130, the national fire code for rail stations, asks that platforms clear within four minutes. Minutes cut from routine clearance widen the margin on a bad day.
Federal taxpayers
The report warns that the new Hudson tunnel’s capacity will be underused if Penn keeps its conflicting moves and long dwells. Phase I delivers up to a third of the added capacity the earlier $16.7 billion expansion promised, for a fraction of that price.
The block south of Penn
Earlier plans to expand Penn called for demolishing much of the block between 30th and 31st Streets, homes, businesses, and the St. John the Baptist church among them. The state stepped back in 2023. Every train Penn gains inside its own walls weakens any future case for taking that block.
Suburban towns
Towns near stations in New Jersey and on Long Island plan new housing around the promise of more frequent trains. That promise runs through a fixed number of slots at Penn. Eight more trains an hour, each able to carry about 1,600 riders on a full-length bilevel set, decides whether a timetable can grow.
Game days and big events
MetLife Stadium and UBS Arena at Belmont draw crowds from across the region. In 2009, Metro-North and NJ Transit ran Train to the Game service from the New Haven Line through Penn to the Meadowlands by special agreement. Routine through-running would make that kind of trip part of the schedule.
Rail workers and their unions
A train from New Jersey to Long Island crosses crew districts, rulebooks, and power systems: NJ Transit runs on overhead AC wire, and LIRR runs on DC third rail. Phase II takes up fleets, labor, and governance, which is where those agreements get written.
Midtown West neighbors and workers
Amtrak and its master developer aim to break ground by the end of 2027. Phase II finishes in 2028. Phase I did not assess construction impacts in detail, so the staging plan will decide how long platforms close and where riders get sent.

What the next phase has to settle

Phase I stayed inside the station walls. The FAQ says Phase II moves out to the Metro-North, LIRR, and NJ Transit service areas and focuses on reliability and operating changes. These are the open items the Phase I documents name or leave untouched.

Arrival reliability

Deferred

This is why Penn Station Future failed simulation: trains arriving off schedule from New Jersey and Long Island break tight through-running slots. The report says going above 32 trains an hour requires regionwide improvements that make trains arrive on time.

Penn Station Future

No owner, no date

The FAQ names no implementer and no timeline for the eight-train package. The Penn Transformation design must preserve space for its future stairs and escalators and avoid new structural columns where tracks could come out.

Fleets and power

Not studied

Trains that run between New Jersey and Long Island need equipment that draws from both overhead AC wire and DC third rail, sized to both railroads’ platforms. Phase I says fleet questions belong to Phase II.

Infrastructure beyond Penn

Not studied

Phase I did not review the railroads’ expansion plans outside the station. Four Gateway projects in New Jersey remain unfunded: Newark–Harrison modernization, the Sawtooth Bridges, Portal South Bridge, and the Secaucus Junction expansion. Yard capacity at West Side Yard and Sunnyside shapes every concept.

Governance and labor

Deferred

One Terminal Operating Plan, a standard train-start procedure, crew agreements across railroads, and clear authority at the Penn Station Control Center.

Who would ride through

Deferred

Phase I treats through-running as an operating tool for capacity. Phase II runs the ridership forecast for trips that cross Manhattan without ending there.

Costs

Not in Phase I

FRA ran a conceptual cost analysis but published no figures; the FAQ says detailed costs come from FRA, Amtrak, and Penn Transformation Partners together, once the developer’s own design and construction savings are known. ENR puts the overall Penn Transformation at $7 to 8 billion.

Construction staging

Not studied

Phase I did not assess construction impacts in detail. Platform closures, track outages, and rider detours during the work remain open.

Model files

Unpublished

The 86 scenarios, the Viriato and RTC timetables and delay runs, and the Viswalk crowd runs are summarized, not released. Dwell inputs trace back to an operating table last revised in December 2013.

West Side Yard

Deferred

Phase I modeled every LIRR train as running to or from West Side Yard, which FRA calls an unlikely real-world plan. The yard’s 30 tracks fill within 60 to 90 minutes of the morning peak, and the Hudson Yards platform built over it rules out growth. That traffic helped sink Penn Station Future in simulation. Phase II tests LIRR trains turning on the platform or more commuter through-running instead.

Eastward extension

Under review

Penn Transformation Partners is studying Platforms 1 and 2 extended up to 450 feet east under Seventh Avenue instead of west. Earlier studies found a Con Edison substation in the Penn 11 basement where the extension would end, and ruled out carrying Tracks 1 to 4 on toward the Sixth Avenue subway because the grade would be far steeper than Amtrak allows. FRA, Amtrak, and the developer have not decided which version the project builds.

Public engagement

Promised

The FAQ commits FRA to public engagement in Phase II, alongside continued work with all five railroads.

The October 2024 railroad engineering study that pointed toward building south of Penn ran no train simulations, according to Amtrak’s February 2026 response to a public-records request for its models. Phase I is the first study to test through-running inside today’s station in a dynamic rail simulator. Every concept FRA carried forward mixes trains that terminate with trains that continue; none asks the station to pick one model.

Dates that lock things in

Construction starts before Phase II finishes. The Penn Transformation design has to keep the Penn Station Future option open: room for future stairs and escalators, and no new columns where tracks could come out.

  1. Oct 2024Railroad partners' feasibility study on doubling trans-Hudson capacity
  2. Apr 17, 2025USDOT puts Amtrak in charge of revitalizing Penn and assigns FRA the Service Optimization Study
  3. Oct 2025FRA starts the study
  4. Mar 26, 2026FRA briefs the three developer teams shortlisted by Amtrak on the Phase I results
  5. May 2026Amtrak selects Penn Transformation Partners as master developer
  6. Jun 2026Phase I analysis complete
  7. Jul 15, 2026FRA releases the Phase I report, with an Addendum on the developer's eastward platform option; Phase II begins
  8. End of 2027Target groundbreaking for Penn Transformation
  9. 2028Phase II complete, with public engagement
  10. 2035Hudson Tunnel Project expected complete
  11. 2038North River Tunnel rehabilitation expected complete

How the model is built

The city. The buildings are New York City’s own 3D building model, which records each building’s roof shape, setbacks, and height from the city’s 2014 aerial survey. The model is checked against the city’s current Building Footprints file. Buildings that no longer stand are removed, including the Hotel Pennsylvania, demolished in 2023. Buildings finished since 2014, among them the Manhattan West and Hudson Yards towers, are added from their current footprint and recorded roof height, so they appear as straight-sided blocks. Roadbeds, parks, and the Hudson shore come from the city’s planimetric maps. No building, street, or structure in the city is invented. Wall colors and window patterns follow each building’s recorded age, height, floor count, and use in the city’s tax-lot file; they are drawn, not photographed. The ground is shown flat.

The station. Every track, switch lead, platform outline, and stub end is traced from the station’s published track and platform diagram, including the Gateway tube leads and the tunnel feeds at both ends. The diagram is drawn with one scale east to west and another north to south. The model fits both scales to the platform outlines mapped in OpenStreetMap, so the station sits at its true size and position: platform ends land within about 5 feet of their mapped positions on ten of the eleven platforms, and model platform widths are within 3 feet of the published widths, except Platform 10. Where the diagram puts two tracks closer than 12 feet, the model spaces them at 12. One unit of the model is 10 feet in every direction. The track level is drawn 46 feet below the street. The model shows no columns, stairs, or ceiling at track level, because no public drawing gives their positions; the blue markers for new stairs and escalators follow FRA’s Figure 11.

The cut. The opening in the ground follows the outline of the tracks. Buildings and streets that stand over that outline, including Madison Square Garden, PENN 2, Moynihan Train Hall, PENN 11, and the Manhattan West towers, fade to outlines when a scene looks at the tracks. Any building that would block the view of the tracks from the camera is cut away the same way.

The trains. Trains follow only connections that exist on the diagram. Train counts follow FRA’s morning-peak tables for trains under the Hudson: 23 in FRA’s baseline timetable today, 32 in Phase I (4 Amtrak, 24 NJ Transit, 4 commuter through), and 32 in Penn Station Future (4 Amtrak, 20 NJ Transit, 8 commuter through). Dwell times come from FRA’s three dwell parameter sets, and track use follows FRA’s platform track access diagrams where the traced connections allow. A route stays locked until the train ahead has fully cleared it, as interlocking signals require, and trains entering or leaving through the same tunnel tube in the same direction run at least 2.5 minutes apart, the tunnel headway FRA’s Phase I timetables use. Trains never exceed 15 mph, the speed limit through the station’s interlockings, and accelerate at about the rate an NJ Transit ALP-45 manages with ten cars. The model does not add the 24-second reset of A Interlocking’s switches. Under these rules the model runs 23 or 24 trains an hour in from the Hudson today, 31 in the Phase I plan, and 26 or 27 in Penn Station Future with every train on time. It brings about 20 LIRR trains an hour in from the East River instead of FRA’s 24. The random lateness in the Penn Station Future scene is the model’s, not a rerun of FRA’s simulation.

The liveries. NJ Transit ALP-45DP engines and MultiLevel coaches, LIRR M7 cars, and Amtrak ACS-64 engines with Amfleet coaches. FRA names no operator for the commuter through trains, so they appear as a generic train with a gold band.

Every number in the text comes from the sources below.